Concrete Pouring Weather in Bend, OR: 10-Day Windows & Best Months

Bend gives you roughly 103 workable concrete pouring days a year, concentrated June through September. The single best month is August, averaging 29 days that clear every check — highs of 83°F, lows near 48°F, and a 7% daily rain chance. Below: the live 10-day check and Bend's full month-by-month table.

Best month: June · 26 workable days

The next 10 days in Bend

GOOD — a clean label day MARGINAL — one borderline check NO — hard fail or stacked flags

The rules this check uses

Typical bagged-mix requirements for small DIY pours, scored against Bend's forecast above. The 48-hour freeze rule dominates every other row; structural work follows engineer/ACI specs instead of this table.

Typical label thresholds for concrete pouring — the ruleset behind every Bend verdict above.
CheckThresholdWhy it matters
Air temperature 40–90°F — ideal 50–85°F DIY pours work from 40–90°F; 50–85°F is the sweet spot.
Overnight low ≥40°F during the first 48 h A low under 40°F inside the first 48 hours puts you in cold-weather concreting — not a DIY window.
Dry before no soaking (≥1.0") in the prior 24 h What fell before you start matters as much as what falls after — surfaces hold water invisibly.
Dry after <0.1" rain for 6 h after (12 h light rain after finishing still risks surface marks) The make-or-break window: rain here undoes the work, not just delays it.
Wind ≤20 mph (rapid surface drying up to 28 mph) Scored on the windiest working hour; the marginal band changes the method, not the day.

Always follow your product label — formulas vary. Treat the table as the consensus range across brands — the label in your hand is the final word.

Best months for concrete pouring in Bend

January: 0 workable days · high 42°F / low 25°F · rain 28% of daysFebruary: 0 workable days · high 46°F / low 24°F · rain 24% of daysMarch: 0 workable days · high 52°F / low 28°F · rain 20% of daysApril: 0 workable days · high 58°F / low 30°F · rain 20% of daysMay: 0 workable days · high 66°F / low 37°F · rain 18% of daysJune: 26 workable days · high 74°F / low 42°F · rain 13% of daysJuly: 29 workable days · high 84°F / low 49°F · rain 8% of daysAugust: 29 workable days · high 83°F / low 48°F · rain 7% of daysSeptember: 19 workable days · high 76°F / low 41°F · rain 8% of daysOctober: 0 workable days · high 63°F / low 34°F · rain 13% of daysNovember: 0 workable days · high 49°F / low 28°F · rain 23% of daysDecember: 0 workable days · high 41°F / low 23°F · rain 27% of daysJanuary avg high 42°FJanuary avg low 25°FFebruary avg high 46°FFebruary avg low 24°FMarch avg high 52°FMarch avg low 28°FApril avg high 58°FApril avg low 30°FMay avg high 66°FMay avg low 37°FJune avg high 74°FJune avg low 42°FJuly avg high 84°FJuly avg low 49°FAugust avg high 83°FAugust avg low 48°FSeptember avg high 76°FSeptember avg low 41°FOctober avg high 63°FOctober avg low 34°FNovember avg high 49°FNovember avg low 28°FDecember avg high 41°FDecember avg low 23°FJanuary: rain on 28% of daysJFebruary: rain on 24% of daysFMarch: rain on 20% of daysMApril: rain on 20% of daysAMay: rain on 18% of daysMJune: rain on 13% of daysJJuly: rain on 8% of daysJAugust: rain on 7% of daysASeptember: rain on 8% of daysSOctober: rain on 13% of daysONovember: rain on 23% of daysNDecember: rain on 27% of daysD23°53°84°0000026292919000
Workable days (bar height)Avg high °FAvg low °FRain odds (dot size)
How Bend months rank: temperature-rule days minus NOAA rain odds, from 1991–2020 normals. An estimate for planning, not a forecast.
MonthAvg highAvg lowRain odds/dayWorkable days 
January 42°F 25°F 28% 0
February 46°F 24°F 24% 0
March 52°F 28°F 20% 0
April 58°F 30°F 20% 0
May 66°F 37°F 18% 0
June 74°F 42°F 13% 26
July 84°F 49°F 8% 29
August 83°F 48°F 7% 29
September 76°F 41°F 8% 19
October 63°F 34°F 13% 0
November 49°F 28°F 23% 0
December 41°F 23°F 27% 0

Bend compresses the whole concrete pouring year into June through September. Miss those 103 workable days and the next real window is months out: by October, average lows hit 34°F against a 40°F floor. Plan the prep work in advance and treat every GOOD chip as spendable. Neighboring towns shift by a month or more — the Oregon comparison shows where Bend sits.

The rain odds swing hard across the year — 7% of days in August up to 28% in January. Season the plan accordingly: prep in the wet months, apply in the dry ones.

Sealing the same driveway later? Sealcoating in Bend wants warmer nights (50°F+) than the pour did.

Climatology here is measured at Bend, Or Us (2.0 km away). Treat the monthly numbers as the neighborhood average; a shaded north-side deck runs colder and damper than any of them. The exact formula lives in the methodology.

The loop continues nearby: check concrete pouring weather in Beaverton, OR one stop back, or Eugene, OR’s concrete pouring windows one stop ahead.

Bend by the numbers

Prep checklist

  1. Clear the 48-hour rule first: two nights over 40°F. June opens that door in Bend; December (23°F average lows) slams it.
  2. Stage everything before mixing: forms braced, base compacted and damp, tools rinsed, help booked.
  3. Cut plastic sheeting and weight it at the pour's edge — Bend sees rain on 7% of August days, and the 6-hour rule doesn't negotiate.
  4. Resist the watery mix: it finishes easier today and dusts forever after. Low slump wins.
  5. Work the sequence: screed on the sheen, float as it dulls, and leave bleed water alone.
  6. Edge and joint with an edger + float set — control joints every 2–3 slab-thicknesses in feet.
  7. Hold the moisture in (sheeting or misting); when September nights dip toward 41°F, a curing blanket is the difference.
  8. Traffic schedule: feet at 24–48 hours, tires near day 7. Anything structural runs on engineer/ACI specs, not this checklist.

Pro moves for Bend conditions

Gear that saves a window

Heads up: product links on this page may become affiliate links when the program is enabled. See the affiliate disclosure.

Frequently asked questions

What temperature is too cold to pour concrete?

The line is a 40°F low inside the first 48 hours; an actual freeze (32°F) physically damages young concrete. Bend's December nights average 23°F — firmly out — while August nights hold near 48°F. Small pours only; structural work follows engineer/ACI specs.

Can you pour concrete before rain?

The engine wants 6 protected hours; light rain later actually feeds the cure. With 28% rain-day odds in January versus 7% in August, Bend's dry-season pours barely think about this rule and wet-season pours live by the radar. For small DIY pours; structural schedules follow ACI.

How long does concrete need to be protected from freezing?

Keep it above freezing for at least the first 48 hours (the engine calls any sub-40°F low in that window a NO). In Bend that rules out roughly December-adjacent months entirely and makes shoulder-season pours a two-night forecast decision. DIY scope; anything structural follows engineer/ACI cold-weather practice.

Is it OK to pour concrete in hot weather?

To a 90°F high, yes — with shade, cool mix water, a damp subgrade, and a dawn start. Above 90°F the surface sets while the core is plastic and shrinkage cracks map the slab. Bend averages 0 such days in July — rarely the binding constraint here.

How long before you can drive on new concrete?

A week before tires, 24–48 hours before feet — at August-typical Bend temperatures (83°F highs). When nights slide toward 23°F, add days: cure speed is temperature. Early loads print permanent marks; the bag's cure table wins every argument.

Best season for concrete work in Bend?

June through september — the months with 40°F+ nights, sub-90°F days, and manageable rain. August leads at 29 workable days; December bottoms out near 0.

How windy is too windy to pour concrete?

Wind matters as much as temperature. Breezes above about 10 to 15 mph, especially with low humidity or warm sun, can evaporate surface moisture faster than bleed water rises — ACI guidance flags evaporation rates above 0.2 pounds per square foot per hour as plastic-shrinkage-cracking territory. For a small DIY slab, wait for a calm morning or rig windbreaks and fog-mist the air above the surface.

How long should I keep new concrete wet?

Keep it continuously wet for at least 7 days — the moist-curing period ACI guidance specifies for conventional concrete (3 days for high-early mixes). Use soaker hoses, wet burlap, curing blankets, or sheet plastic, or spray on a curing compound after finishing. Concrete allowed to dry out early can lose a large share of its potential strength and is far more likely to dust, scale, and crack.

When can I remove the forms from a small concrete pour?

For slabs, walkways, and post footings, side forms can usually come off 24 to 48 hours after the pour — leave them at least 72 hours when temperatures run below 50°F, since strength gain slows dramatically. Pry against the ground, never the green concrete, and keep curing the exposed edges afterward. Forms supporting structural or suspended concrete follow engineering rules, not DIY timelines.

How soon can I seal new concrete?

Wait until it reaches full cure — about 28 days — before applying most penetrating or acrylic sealers; sealing earlier traps moisture and can cause clouding or poor bond. The exception is a cure-and-seal product designed to go on the day of the pour. Pick a dry stretch with temperatures roughly 50 to 90°F — in Bend, June typically offers the most reliable window — so the sealer itself cures properly.

Concrete Pouring glossary

Evaporation rate
How fast surface moisture leaves fresh concrete, driven by temperature, wind, and humidity; rates above about 0.2 lb per square foot per hour invite plastic shrinkage cracking.
Plastic shrinkage cracking
Shallow, random cracks forming within hours of placement when the surface dries faster than bleed water can replace it; wind and sun are the usual culprits.
Bleed water
Mix water that rises to the surface after placement; finishing before it evaporates traps it under the trowel, creating a weak, dusty top layer.
Hydration
The chemical reaction between cement and water that hardens concrete; it needs moisture and temperatures above roughly 40°F, and continues gaining strength for weeks.
Curing compound
A sprayed or rolled membrane that seals moisture inside fresh concrete when wet curing isn't practical; some types must be stripped before paint or sealer.
Air entrainment
Microscopic air bubbles added to the mix that give exterior concrete freeze-thaw and deicer resistance; it must be ordered in the mix, not added later.

People also search for

Other projects in Bend

Concrete Pouring nearby

Guides

Climatology: NOAA 1991–2020 normals via BEND, OR US (2.0 km from Bend center, elevation 3660 ft); live outlook by Open-Meteo.