WorkWindow

Concrete Pouring · Texas

Concrete Pouring Weather in Wichita Falls, TX: 10-Day Windows & Best Months

Wichita Falls gives you roughly 120 workable concrete pouring days a year, concentrated March through May. The single best month is October, averaging 25 days that clear every check — highs of 77°F, lows near 52°F, and a 21% daily rain chance. Below: the live 10-day check and Wichita Falls's full month-by-month table.

Best month: April · 23 workable days

The next 10 days in Wichita Falls

GOOD — a clean label day MARGINAL — one borderline check NO — hard fail or stacked flags

The rules this check uses

Typical bagged-mix requirements for small DIY pours, scored against Wichita Falls's forecast above. The 48-hour freeze rule dominates every other row; structural work follows engineer/ACI specs instead of this table.

Typical label thresholds for concrete pouring — the ruleset behind every Wichita Falls verdict above.
CheckThresholdWhy it matters
Air temperature 40–90°F — ideal 50–85°F DIY pours work from 40–90°F; 50–85°F is the sweet spot.
Overnight low ≥40°F during the first 48 h A low under 40°F inside the first 48 hours puts you in cold-weather concreting — not a DIY window.
Dry before no soaking (≥1.0") in the prior 24 h What fell before you start matters as much as what falls after — surfaces hold water invisibly.
Dry after <0.1" rain for 6 h after (12 h light rain after finishing still risks surface marks) The make-or-break window: rain here undoes the work, not just delays it.
Wind ≤20 mph (rapid surface drying up to 28 mph) Scored on the windiest working hour; the marginal band changes the method, not the day.

Always follow your product label — formulas vary. Treat the table as the consensus range across brands — the label in your hand is the final word.

Best months for concrete pouring in Wichita Falls

January: 0 workable days · high 55°F / low 30°F · rain 15% of daysFebruary: 0 workable days · high 59°F / low 34°F · rain 18% of daysMarch: 17 workable days · high 68°F / low 42°F · rain 20% of daysApril: 23 workable days · high 76°F / low 50°F · rain 23% of daysMay: 22 workable days · high 84°F / low 60°F · rain 28% of daysJune: 4 workable days · high 92°F / low 68°F · rain 25% of daysJuly: 0 workable days · high 97°F / low 72°F · rain 17% of daysAugust: 0 workable days · high 97°F / low 72°F · rain 19% of daysSeptember: 16 workable days · high 88°F / low 64°F · rain 21% of daysOctober: 25 workable days · high 77°F / low 52°F · rain 21% of daysNovember: 12 workable days · high 65°F / low 40°F · rain 18% of daysDecember: 0 workable days · high 56°F / low 32°F · rain 15% of daysJanuary avg high 55°FJanuary avg low 30°FFebruary avg high 59°FFebruary avg low 34°FMarch avg high 68°FMarch avg low 42°FApril avg high 76°FApril avg low 50°FMay avg high 84°FMay avg low 60°FJune avg high 92°FJune avg low 68°FJuly avg high 97°FJuly avg low 72°FAugust avg high 97°FAugust avg low 72°FSeptember avg high 88°FSeptember avg low 64°FOctober avg high 77°FOctober avg low 52°FNovember avg high 65°FNovember avg low 40°FDecember avg high 56°FDecember avg low 32°FJanuary: rain on 15% of daysJFebruary: rain on 18% of daysFMarch: rain on 20% of daysMApril: rain on 23% of daysAMay: rain on 28% of daysMJune: rain on 25% of daysJJuly: rain on 17% of daysJAugust: rain on 19% of daysASeptember: rain on 21% of daysSOctober: rain on 21% of daysONovember: rain on 18% of daysNDecember: rain on 15% of daysD30°63°97°001723224001625120
Workable days (bar height)Avg high °FAvg low °FRain odds (dot size)
How Wichita Falls months rank: temperature-rule days minus NOAA rain odds, from 1991–2020 normals. An estimate for planning, not a forecast.
MonthAvg highAvg lowRain odds/dayWorkable days 
January 55°F 30°F 15% 0
February 59°F 34°F 18% 0
March 68°F 42°F 20% 17
April 76°F 50°F 23% 23
May 84°F 60°F 28% 22
June 92°F 68°F 25% 4
July 97°F 72°F 17% 0
August 97°F 72°F 19% 0
September 88°F 64°F 21% 16
October 77°F 52°F 21% 25
November 65°F 40°F 18% 12
December 56°F 32°F 15% 0

Figure 120 workable days a year in Wichita Falls, spread across March through May. Shoulder months turn on the overnight rule: an afternoon at 68°F passes, but the 40°F night floor is what actually opens the season in March. Neighboring towns shift by a month or more — the Texas comparison shows where Wichita Falls sits.

July here fails on heat, not rain: the average high of 97°F sits over the 90°F label ceiling, and 31 of 31 days typically top 90°F. Midsummer work moves to dawn or waits for October.

Sealing the same driveway later? Sealcoating in Wichita Falls wants warmer nights (50°F+) than the pour did.

Climatology here is measured at Wichita Falls Muni Ap, Tx Us (8.6 km away). Treat the monthly numbers as the neighborhood average; a shaded north-side deck runs colder and damper than any of them. The exact formula lives in the methodology.

For contrast, Waco, TX’s concrete pouring calendar sits one stop back on this route, and concrete pouring in Layton, UT is next in line.

Wichita Falls by the numbers

Prep checklist

  1. Clear the 48-hour rule first: two nights over 40°F. March opens that door in Wichita Falls; January (30°F average lows) slams it.
  2. Stage everything before mixing: forms braced, base compacted and damp, tools rinsed, help booked.
  3. Cut plastic sheeting and weight it at the pour's edge — Wichita Falls sees rain on 21% of October days, and the 6-hour rule doesn't negotiate.
  4. Resist the watery mix: it finishes easier today and dusts forever after. Low slump wins.
  5. Work the sequence: screed on the sheen, float as it dulls, and leave bleed water alone.
  6. Edge and joint with an edger + float set — control joints every 2–3 slab-thicknesses in feet.
  7. Hold the moisture in (sheeting or misting); when May nights dip toward 60°F, a curing blanket is the difference.
  8. Traffic schedule: feet at 24–48 hours, tires near day 7. Anything structural runs on engineer/ACI specs, not this checklist.

Pro moves for Wichita Falls conditions

Gear that saves a window

Heads up: product links on this page may become affiliate links when the program is enabled. See the affiliate disclosure.

Frequently asked questions

What temperature is too cold to pour concrete?

The line is a 40°F low inside the first 48 hours; an actual freeze (32°F) physically damages young concrete. Wichita Falls's January nights average 30°F — firmly out — while October nights hold near 52°F. Small pours only; structural work follows engineer/ACI specs.

Can you pour concrete before rain?

The engine wants 6 protected hours; light rain later actually feeds the cure. With 28% rain-day odds in May versus 15% in January, Wichita Falls's dry-season pours barely think about this rule and wet-season pours live by the radar. For small DIY pours; structural schedules follow ACI.

How long does concrete need to be protected from freezing?

Keep it above freezing for at least the first 48 hours (the engine calls any sub-40°F low in that window a NO). In Wichita Falls that rules out roughly January-adjacent months entirely and makes shoulder-season pours a two-night forecast decision. DIY scope; anything structural follows engineer/ACI cold-weather practice.

Is it OK to pour concrete in hot weather?

To a 90°F high, yes — with shade, cool mix water, a damp subgrade, and a dawn start. Above 90°F the surface sets while the core is plastic and shrinkage cracks map the slab. Wichita Falls averages 31 such days in July, which is why summer pours here move to first light.

How long before you can drive on new concrete?

A week before tires, 24–48 hours before feet — at October-typical Wichita Falls temperatures (77°F highs). When nights slide toward 30°F, add days: cure speed is temperature. Early loads print permanent marks; the bag's cure table wins every argument.

Best season for concrete work in Wichita Falls?

The table above says October, April and May: enough warmth for the 48-hour cure, short of the 90°F ceiling. For small DIY pours that's the whole answer; structural pours schedule to engineer/ACI requirements, not to a best-months chart.

How windy is too windy to pour concrete?

Wind matters as much as temperature. Breezes above about 10 to 15 mph, especially with low humidity or warm sun, can evaporate surface moisture faster than bleed water rises — ACI guidance flags evaporation rates above 0.2 pounds per square foot per hour as plastic-shrinkage-cracking territory. For a small DIY slab, wait for a calm morning or rig windbreaks and fog-mist the air above the surface.

How long should I keep new concrete wet?

Keep it continuously wet for at least 7 days — the moist-curing period ACI guidance specifies for conventional concrete (3 days for high-early mixes). Use soaker hoses, wet burlap, curing blankets, or sheet plastic, or spray on a curing compound after finishing. Concrete allowed to dry out early can lose a large share of its potential strength and is far more likely to dust, scale, and crack.

When can I remove the forms from a small concrete pour?

For slabs, walkways, and post footings, side forms can usually come off 24 to 48 hours after the pour — leave them at least 72 hours when temperatures run below 50°F, since strength gain slows dramatically. Pry against the ground, never the green concrete, and keep curing the exposed edges afterward. Forms supporting structural or suspended concrete follow engineering rules, not DIY timelines.

How soon can I seal new concrete?

Wait until it reaches full cure — about 28 days — before applying most penetrating or acrylic sealers; sealing earlier traps moisture and can cause clouding or poor bond. The exception is a cure-and-seal product designed to go on the day of the pour. Pick a dry stretch with temperatures roughly 50 to 90°F — in Wichita Falls, April typically offers the most reliable window — so the sealer itself cures properly.

Concrete Pouring glossary

Evaporation rate
How fast surface moisture leaves fresh concrete, driven by temperature, wind, and humidity; rates above about 0.2 lb per square foot per hour invite plastic shrinkage cracking.
Plastic shrinkage cracking
Shallow, random cracks forming within hours of placement when the surface dries faster than bleed water can replace it; wind and sun are the usual culprits.
Bleed water
Mix water that rises to the surface after placement; finishing before it evaporates traps it under the trowel, creating a weak, dusty top layer.
Hydration
The chemical reaction between cement and water that hardens concrete; it needs moisture and temperatures above roughly 40°F, and continues gaining strength for weeks.
Curing compound
A sprayed or rolled membrane that seals moisture inside fresh concrete when wet curing isn't practical; some types must be stripped before paint or sealer.
Air entrainment
Microscopic air bubbles added to the mix that give exterior concrete freeze-thaw and deicer resistance; it must be ordered in the mix, not added later.

People also search for

Other projects in Wichita Falls

Concrete Pouring nearby

Guides

Climatology: NOAA 1991–2020 normals via WICHITA FALLS MUNI AP, TX US (8.6 km from Wichita Falls center, elevation 1017 ft); live outlook by Open-Meteo.