Concrete Pouring Weather in Wichita Falls, TX: 10-Day Windows & Best Months
Wichita Falls gives you roughly 120 workable concrete pouring days a year, concentrated March through May. The single best month is October, averaging 25 days that clear every check — highs of 77°F, lows near 52°F, and a 21% daily rain chance. Below: the live 10-day check and Wichita Falls's full month-by-month table.
GOOD — a clean label day MARGINAL — one borderline check NO — hard fail or stacked flags
The rules this check uses
Typical bagged-mix requirements for small DIY pours, scored against Wichita Falls's forecast above. The 48-hour freeze rule dominates every other row; structural work follows engineer/ACI specs instead of this table.
| Check | Threshold | Why it matters |
|---|---|---|
| Air temperature | 40–90°F — ideal 50–85°F | DIY pours work from 40–90°F; 50–85°F is the sweet spot. |
| Overnight low | ≥40°F during the first 48 h | A low under 40°F inside the first 48 hours puts you in cold-weather concreting — not a DIY window. |
| Dry before | no soaking (≥1.0") in the prior 24 h | What fell before you start matters as much as what falls after — surfaces hold water invisibly. |
| Dry after | <0.1" rain for 6 h after (12 h light rain after finishing still risks surface marks) | The make-or-break window: rain here undoes the work, not just delays it. |
| Wind | ≤20 mph (rapid surface drying up to 28 mph) | Scored on the windiest working hour; the marginal band changes the method, not the day. |
Always follow your product label — formulas vary. Treat the table as the consensus range across brands — the label in your hand is the final word.
Best months for concrete pouring in Wichita Falls
| Month | Avg high | Avg low | Rain odds/day | Workable days | |
|---|---|---|---|---|---|
| January | 55°F | 30°F | 15% | 0 | |
| February | 59°F | 34°F | 18% | 0 | |
| March | 68°F | 42°F | 20% | 17 | |
| April | 76°F | 50°F | 23% | 23 | |
| May | 84°F | 60°F | 28% | 22 | |
| June | 92°F | 68°F | 25% | 4 | |
| July | 97°F | 72°F | 17% | 0 | |
| August | 97°F | 72°F | 19% | 0 | |
| September | 88°F | 64°F | 21% | 16 | |
| October | 77°F | 52°F | 21% | 25 | |
| November | 65°F | 40°F | 18% | 12 | |
| December | 56°F | 32°F | 15% | 0 |
Figure 120 workable days a year in Wichita Falls, spread across March through May. Shoulder months turn on the overnight rule: an afternoon at 68°F passes, but the 40°F night floor is what actually opens the season in March. Neighboring towns shift by a month or more — the Texas comparison shows where Wichita Falls sits.
July here fails on heat, not rain: the average high of 97°F sits over the 90°F label ceiling, and 31 of 31 days typically top 90°F. Midsummer work moves to dawn or waits for October.
Sealing the same driveway later? Sealcoating in Wichita Falls wants warmer nights (50°F+) than the pour did.
Climatology here is measured at Wichita Falls Muni Ap, Tx Us (8.6 km away). Treat the monthly numbers as the neighborhood average; a shaded north-side deck runs colder and damper than any of them. The exact formula lives in the methodology.
Wichita Falls by the numbers
- Peak heat lands in July: 97°F average highs and 31 ninety-degree days.
- January bottoms the Wichita Falls year: 55°F days, 30°F nights.
- Rain-day odds swing from 15% in January to 28% in May.
- Nights averaging 40°F+ run March through November.
- Annual workable concrete pouring days: about 120 of 365.
Prep checklist
- Clear the 48-hour rule first: two nights over 40°F. March opens that door in Wichita Falls; January (30°F average lows) slams it.
- Stage everything before mixing: forms braced, base compacted and damp, tools rinsed, help booked.
- Cut plastic sheeting and weight it at the pour's edge — Wichita Falls sees rain on 21% of October days, and the 6-hour rule doesn't negotiate.
- Resist the watery mix: it finishes easier today and dusts forever after. Low slump wins.
- Work the sequence: screed on the sheen, float as it dulls, and leave bleed water alone.
- Edge and joint with an edger + float set — control joints every 2–3 slab-thicknesses in feet.
- Hold the moisture in (sheeting or misting); when May nights dip toward 60°F, a curing blanket is the difference.
- Traffic schedule: feet at 24–48 hours, tires near day 7. Anything structural runs on engineer/ACI specs, not this checklist.
Gear that saves a window
Heads up: product links on this page may become affiliate links when the program is enabled. See the affiliate disclosure.
-
Edger + float set
Rounded edges and a flat surface before it sets.
-
Curing blanket
Holds heat through cold nights in the critical 48 hours.
-
IR surface thermometer
Track slab temperature, not just the forecast.
-
Plastic sheeting
Emergency rain cover and moisture-holding cure layer.
FAQ
What temperature is too cold to pour concrete?
The line is a 40°F low inside the first 48 hours; an actual freeze (32°F) physically damages young concrete. Wichita Falls's January nights average 30°F — firmly out — while October nights hold near 52°F. Small pours only; structural work follows engineer/ACI specs.
Can you pour concrete before rain?
The engine wants 6 protected hours; light rain later actually feeds the cure. With 28% rain-day odds in May versus 15% in January, Wichita Falls's dry-season pours barely think about this rule and wet-season pours live by the radar. For small DIY pours; structural schedules follow ACI.
How long does concrete need to be protected from freezing?
Keep it above freezing for at least the first 48 hours (the engine calls any sub-40°F low in that window a NO). In Wichita Falls that rules out roughly January-adjacent months entirely and makes shoulder-season pours a two-night forecast decision. DIY scope; anything structural follows engineer/ACI cold-weather practice.
Is it OK to pour concrete in hot weather?
To a 90°F high, yes — with shade, cool mix water, a damp subgrade, and a dawn start. Above 90°F the surface sets while the core is plastic and shrinkage cracks map the slab. Wichita Falls averages 31 such days in July, which is why summer pours here move to first light.
How long before you can drive on new concrete?
A week before tires, 24–48 hours before feet — at October-typical Wichita Falls temperatures (77°F highs). When nights slide toward 30°F, add days: cure speed is temperature. Early loads print permanent marks; the bag's cure table wins every argument.
Best season for concrete work in Wichita Falls?
The table above says October, April and May: enough warmth for the 48-hour cure, short of the 90°F ceiling. For small DIY pours that's the whole answer; structural pours schedule to engineer/ACI requirements, not to a best-months chart.
Related
Other projects in Wichita Falls
- Deck Staining in Wichita Falls
- Exterior Painting in Wichita Falls
- Driveway Sealing in Wichita Falls
- Roof Coating in Wichita Falls
- Lawn Seeding in Wichita Falls
- All outdoor project weather in Wichita Falls
Concrete Pouring nearby
Guides
Climatology: NOAA 1991–2020 normals via WICHITA FALLS MUNI AP, TX US (8.6 km from Wichita Falls center, elevation 1017 ft); live outlook by Open-Meteo.